• Project Scope

    We completed public stormwater, wastewater and watermain infrastructure for this 3-lot residential subdivision in Torbay. The works included a 225mm concrete stormwater pipeline crossing the road diagonally and connecting to an existing 300mm concrete stormwater pipe and manhole on the opposite side. A separate wastewater trench connected to an existing 150mm AC pipe, with both connections serving Lots 1–3.

    Site Challenges

    The work was carried out in a restricted driveway area beside an existing house, leaving limited space for excavation and site operations. The boundary-outside works involved crossing the road and working around numerous existing underground services, including high-voltage cables, power, gas and telecommunications.

    The stormwater road crossing was the most challenging part of the project. Auckland Transport and Council requirements were strict, with inspections at each stage and geotechnical reports required throughout the works. Excavation also had to be completed in a stepped formation to meet geotechnical requirements.

    Construction Approach

    We carefully planned and progressed the works around the existing underground services and restricted site access. The excavation was carried out in stages, following the required stepped formation and geotechnical inspection process. Our team coordinated the stormwater road crossing, the separate wastewater connection and the associated infrastructure works, while meeting the required inspection and road reinstatement standards.

    Project Completion

    The project took three weeks to complete. We successfully delivered the public stormwater, wastewater and watermain works, including the road crossing and connections to the existing networks. Despite the restricted working space, congested underground services and demanding inspection and reinstatement requirements, the project was completed successfully.

  • Related Projects of Drainage works

    Blockhouse Bay – 5-Lot Residential Subdivision

    Birkenhead – 8-Lot Subdivision & Directional Drilling

    Ti Rakau Drive, Pakuranga - 9-Lot Residential Subdivision

    Northshore | 5-Lot Residential Subdivision Drainage Works

    Woodglen, Glen Eden | 61-Lot Residential Subdivision

    West Harbour | Deep Public Drainage Infrastructure Works

    14 Diana Dr, Glenfield | 20-Lot Residential Development

    Arabi St, Sandringham | 10-Lot Residential Development

    32 Lavery Place, Sunnynook | 4-Lot Residential Subdivision

    New Windsor | Public Stormwater Pipe Replacement

    New North Road | 4 Lot Residential Subdivision

    Wicklam Lane, Greenhithe | 15-Lot Farm Subdivision – Stage 1

    4 Emirau Place, Glenfield – 5-Lot Residential Subdivision

    3 Summit Drive, Torbay – 3-Lot Residential Subdivision